1
|
2243/2024
|
Jodhpur Vidyut Vitran Nigam Limited.
|
petition for approval of levelized tariff discovered through transparent competitive bidding carried out by JdVVNL for solar power projects under Component-C (Feeder Level Solarization) of Pm-Kusum Scheme
|
11/09/2024
|
|
2
|
2244/2024
|
Jaipur Vidyut Vitran Nigam Limited
|
Petition for approval of levelized tariff discovered through transparent competitive bidding carried out by JVVNL for solar power projects with aggregate capacity of 208.91 MW under Component-C (Feeder Level Solarization) of PM-KUSUM Scheme
|
11/09/2024
|
|
3
|
2240/2024
|
Suo Motu
|
In the matter of the RERC (Grid Interactive Distributed Renewable Energy Generating Systems) (Second Amendment) Regulations, 2024.
|
25/07/2024
|
|
4
|
2212/2024
|
Rajasthan Urja Vikas and IT Services Limited
|
Petition seeking approval of procurement of 300 MW Solar Power from NLC India Ltd., under the Central Public Sector Undertaking (CPSU) scheme of the Ministry of New and Renewable Energy
|
24/07/2024
|
|
5
|
2231/2024
|
Rajasthan Urja Vikas and IT Services Limited
|
Petition for approval of procurement of 500 MW Solar Power from SJVN Green Energy Ltd., under the Central Public Sector Undertaking (CPSU) Scheme of the Ministry of New and Renewable Energy.
|
24/07/2024
|
|
6
|
2218/2024
|
Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
|
Petition for allowing additional expenditure for disposal of Ash from RVUN power plants in pursuant to the MoEF and CC, GoI Notifications
|
19/07/2024
|
|
7
|
2232/2024
|
Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
|
Petition for removal of difficulty under section 11, 61,62 and 86 (1) (a) of Electricity Act, 2003 read with Regulation 95 of RERC Tariff Regulations, 2019 and other powers enabling it in this behalf for allowing Interim Energy Charges Rate (ECR) for DCCPP.
|
18/07/2024
|
|
8
|
2172/2023
|
Rajasthan Urja Vikas and IT Service Limited
|
Petition for approval for tie up of 1000MW / 6000 MWh per day (continuous discharge of 4 hours) on long term basis from Pump Storage based energy storage
|
16/07/2024
|
|
9
|
2228/2024
|
Rajasthan Urja Vikas and IT Service Limited
|
Petition filed in the matter of seeking approval of procurement of 1000 MW Solar Power from Respondents as per guidelines issued by Ministry of New and Renewable Energy.
|
10/07/2024
|
|
10
|
2024/2022
|
Discoms
|
Petition to recognize Additional Power Purchase Cost incurred in order to comply with the orders of Honble Supreme Court in the matter of change in law and allow recovery of additional power purchase cost through special FSA
|
01/07/2024
|
|
11
|
2230/2024
|
Rajasthan Urja Vikas and IT Service Limited and Ors.
|
Petition for approval of amendment in the original PPA and adoption and approval of the Tariff of 50 percent of generation to be now sold to petitioners by virtue of amendment in the PPA.
|
27/06/2024
|
|
12
|
2217/2024
|
BG Wind Power Limited
|
Petition filed under Section 86(1) (f) of the Electricity Act, 2003
|
20/06/2024
|
|
13
|
1373/2018
|
Adani Power Limited
|
Petition filed for determining the compensation/tariff adjustment under Section 86 of the Electricity Act, 2003 read with Article 10 Change in Law of the PPA executed with Discoms
|
19/06/2024
|
|
14
|
2234/2024
|
SUO MOTU
|
RERC (RE Certificate and RPO compliance framework), Regulations, 2010
|
31/05/2024
|
|
15
|
2235/2024
|
SUO MOTU
|
In the matter of RERC (Grid Interactive Distributed Renewable Energy Generating Systems) Regulations, 2021
|
31/05/2024
|
|
16
|
2198/2024
|
Bharat Petroleum Corporation Ltd.
|
Petition filed for updating tariff Regulations of power Distribution Companies in Rajanthan so as to provide lt connections to the electric vehicle charging stations to be set up by oil marketing companies
|
30/04/2024
|
|
17
|
2167/2023
|
Maharaja Shree Umaid Mills Limited
|
In the matter of Petition filed u/s 86(1) (f) of the Electricity Act, 2003 for adjudication of dispute
|
02/04/2024
|
|
18
|
2147/2023
|
Transtech Green Power Pvt. Ltd.
|
Petition filed under Section 86(1)(f) read with Sec.142 of the Electricity Act for adjudication of dispute.
|
26/03/2024
|
|
19
|
2181/2023
|
Rajasthan Urja Vikas Nigam Limited
|
Application for Modification/clarification of the order dated 27.07.2023 passed by the Commission in Petition No. RERC/2139/2023
|
19/03/2024
|
|
20
|
2150/2023
|
Kisan Urja Hitkari Samiti
|
Petition filed u/s. 86 of the Electricity Act, 2003 r/w. Article. 12.2 r/w Article 12 of the PPAs, executed by RPGs with Discoms through the Respondent under PM KUSUM Yojna Component-A of Capacity 0.5 MW to 2.0 MW in the State of Rajasthan, for allowing carrying cost
|
19/03/2024
|
|
21
|
2180/2023
|
M/s Hindustan Zinc Limited, Udaipur
|
In the matter of petition under section 50 and section 86 (1) (a), (k) and section 181(1), (2)(x) of the Electricity Act, 2003 read with Regulation 14.1 of RERC (Electricity Supply Code and Connected Matters) Regulations, 2021 read with Regulation 72, 73, 76 of the RERC (Conduct of Business) Regulations, 2000 seeking orders for modification of rate of Late Payment Surcharge/Delayed Payment Surcharge
|
19/03/2024
|
|
22
|
2186/2023
|
M/s Sangod Transmission Service Limited
|
In the matter of application filed by M/s Sangod Transmission Service Limited for grant of Transmission Licence
|
05/03/2024
|
|
23
|
2186/2023
|
M/s Sangod Transmission Service Limited
|
In the matter of application filed by Sangod Transmission Service Limited for grant of Transmission Licence
|
23/02/2024
|
|
24
|
2185/2023
|
Sangod Transmission Service Limited
|
Petition for adoption of Transmission Charges with respect to the Transmission System being established by Sangod Transmission Service Limited.
|
20/02/2024
|
|
25
|
2144/2023
|
Link Enterprises
|
Petition for adjudication of dispute under Section 86 (1) (f) of the Electricity Act, 2003
|
20/02/2024
|
|
26
|
2145/2023
|
Link Enterprises
|
Petition for adjudication of dispute under Section 86 (1) (f) of the Electricity Act, 2003
|
20/02/2024
|
|
27
|
2168/2023
|
Rajasthan Rajya Vidyut Prasaran Nigam Ltd
|
Petition for removal of difficulties and seeking amendment in RERC (Terms and Conditions of Open Access) Regulations, 2016.
|
13/02/2024
|
|
28
|
2201/2024
|
Suo motu
|
In the matter of Rajasthan Electricity Regulatory Commission (Grid Interactive Distributed Renewable Energy Generating Systems) Regulations, 2021.
|
07/02/2024
|
|
29
|
2130/2023
|
M/s Hindustan Zinc Limited
|
Petition challenging the conduct of Ajmer Vidyut Vitran Nigam Ltd (AVVNL) for restricting generation of a captive power plant
|
02/02/2024
|
|
30
|
2190/2023
|
Jaipur Vidyut Vitran Nigam Ltd.
|
Petition to make necessary amendments in the existing spot generated consumer bill format and removal of difficulties
|
30/01/2024
|
|
31
|
2177/2023
|
Pioneer Non Fried Foods Private Limited
|
Petition filed for compliance of Ombudsman order
|
11/01/2024
|
|
32
|
2152/2023
|
Ajay Mines and Minerals
|
Petition filed for compliance of Ombudsman order.
|
09/01/2024
|
|
33
|
2127/2023
|
Discoms
|
In the matter of approval of temporary suspension of Time of Day (ToD) rebate under Regulation 87(3) and 95 of the RERC (Terms and Conditions for Determination of Tariff) Regulations, 2019
|
05/01/2024
|
|
34
|
2120/2023
|
Discoms
|
In the matter of seeking approval for levying Green Power Tariff for supply of renewable energy (RE) to consumers opting for 100 percent green energy to meet their demand.
|
04/01/2024
|
|
35
|
2119/2023
|
Discoms
|
In the matter of seeking approval of power purchase from short term sources for Rajasthan Discoms
|
04/01/2024
|
|
36
|
2101/2023
|
Rajasthan Urja Vikas Nigam Ltd.
|
Petition for determining the tariff of Biomass Power Plants based on Rankine Cycle Technology
|
04/01/2024
|
|
37
|
2082/2023
|
Onevolt Energy Pvt. Limited and Ors
|
Petition for seeking declaration cum directions on the condition(s) applicable for qualifying as a captive generating plant in the State of Rajasthan.
|
03/01/2024
|
|
38
|
2146/2023
|
J. K. Lakshmi Cement Limited
|
Petition for direction to the Respondent RUVNL to make the payment of the power injected into the Grid
|
03/01/2024
|
|
39
|
2131/2023
|
Kalpataru Power Transmission Limited
|
Petition for determination of Tariff for 10 years beyond 15.07.2023 for Biomass Power Plant commissioned under Government of Rajasthan, Policy, 1999.
|
02/01/2024
|
|
40
|
2039/2022
|
J K Cement Ltd
|
Petition filed under Section 142 of the Electricity Act, 2003 by not according Captive Power Plant (CPP) status
|
26/12/2023
|
|
41
|
2189/2023
|
Discoms
|
In the matter of petition filed under Section 86 (1) and 181 of the Electricity Act, 2003 read with Regulation 1.2 and 14.1 of Rajasthan Electricity Regulatory Commission (Electricity Supply Code and Connected Matters) Regulations, 2021 to make necessary amendments in the said Regulations to remove the difficulties faced by Discoms and Consumers in implementation of the said regulations regarding provision of mandatory submission of stamp paper while applying for new service connection/supply.
|
20/12/2023
|
|
42
|
2173/2023
|
Rajasthan Urja Vikas Nigam Ltd and Ors.
|
Review Petition under Section 94(1) (f) of the Electricity Act, 2003 for review read with Regulation 34,50,51 of RERC (Transaction of Business) Regulations, 2021 for review in the order dated 04.07.2023
|
19/12/2023
|
|
43
|
2047/2022
|
UltraTech cement Limited and Anr.
|
In the matter of Petition filed under Section 9, 42 and 86 of the Electricity Act, 2003 read with Rule 3 of the Electricity Rules and Regulation 18 of the Conduct of Business Regulations 2000 and Regulation 19 of the Transaction of Business Regulations 2021 challenging the illegal and arbitrary levy of cross Subsidy Surcharge, Additional Surcharge and Water Cess.
|
14/12/2023
|
|
44
|
2153/2023
|
Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
|
Petition seeking In-Principle approval for installation of Sewage Treatment Plant at Kota Super Thermal Power Station (KSTPS)
|
12/12/2023
|
|
45
|
2135/2023
|
Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
|
Petition filed under Regulation 17(3) of RERC Tariff Regulation, 2019 seeking In-Principle approval of Additional Capitalization for up-gradation of DCS HMI System and network switches along with Performance Analysis Diagnostics and Optimization (PADO) System at Kalisindh Thermal Power Station.
|
08/12/2023
|
|
46
|
2169/2023
|
Suo Motu
|
In the matter of the RERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) (Second Amendment) Regulations, 2023
|
08/12/2023
|
|
47
|
2123/2023
|
Discoms
|
In the matter of approval of recovery of Fuel Surcharge over and above ceiling limit for Quarter 4 of FY 2023, as per Regulation 88 of the Rajasthan Electricity Regulatory Commission ( Terms and Conditions for Determination of Tariff ) Regulations, 2019 issued by Rajasthan Electricity Regulatory Commission under section 61 read with Section 181 of the Electricity Act, 2003.
|
06/12/2023
|
|
48
|
2056/2022
|
Rajasthan Urja Vikas Nigam Ltd
|
Petition seeking approval for procurement of 105.4 MW power from Biomass Plants in the Rajasthan State under Policy for Promoting Generation of Electricity from Biomass, 2010 for meeting the RPO requirements of the state.
|
24/11/2023
|
|
49
|
2179/2023
|
Jodhpur Vidyut Vitran Nigam Limited
|
Petition for approval of Levelized Tariff Discovered Through Transparent Competitive Bidding carried out by JDVVNL for solar power projects under Component-C (Feeder Level Solarization) of PM-KUSUM Scheme
|
24/11/2023
|
|
50
|
2143/2023
|
Sh. Rakesh Singh
|
Petition for review the ceiling levelised tariff fixed for PV Solar Power Plant to be set-up under PM KUSUM Yojna Component-C and for Approval of Levelized Tariff discovered through transparent Competitive Bidding carried out by JVVNL for Solar Power Projects with aggregate capacity of 52.66 MW under Component-C (Feeder Level Solarization) of PM-KUSUM Scheme
|
17/11/2023
|
|
51
|
2132/2023
|
Dharmender Kumar
|
Petition for review and rectification of errors in the levelised tariff fixed for PV Solar Power Plant and for determination of compensation/adjustment in levelised tariff on account of Change in Law events to be set -up under PM Kusum Yojna Component-C.
|
16/11/2023
|
|
52
|
2114/2023
|
M/s Oil India Limited
|
Petition filed in the matter of adjudication of dispute under Section 86 (1) (f) of the Electricity Act, 2003.
|
16/11/2023
|
|
53
|
2115/2023
|
M/s Oil India Limited
|
Petition filed in the matter of adjudication of dispute under Section 86 (1) (f) of the Electricity Act, 2003.
|
16/11/2023
|
|
54
|
2102/2023
|
Indian Oil Corporation Limited
|
Petition filed in the matter of adjudication of dispute under Section 86 (1) (f) of the Electricity Act, 2003.
|
01/11/2023
|
|
55
|
2103/2023
|
Indian Oil Corporation Limited
|
Petition filed in the matter of adjudication of dispute under Section 86 (1) (f) of the Electricity Act, 2003.
|
01/11/2023
|
|
56
|
2104/2023
|
Indian Oil Corporation Limited
|
Petition filed in the matter of adjudication of dispute under Section 86 (1) (f) of the Electricity Act, 2003.
|
01/11/2023
|
|
57
|
2149/2023
|
M/s Bosch Limited
|
Petition under Section 86(1) (e) read with Sec.142 of the Electricity Act for adjudication of dispute
|
30/10/2023
|
|
58
|
1814/2020
|
Balkrishna Industries Limited Bhiwadi
|
Petition filed under Section 142 of the Electricity Act, 2003 for non-compliance of Ombudsman order dated 25.04.2014
|
26/10/2023
|
|
59
|
1813/2020
|
M/s Balkrishna Industries Limited, Chopanki
|
Petition filed under Section 142 of the Electricity Act, 2003 for non-compliance of Ombudsman order dated 25.04.2014
|
26/10/2023
|
|
60
|
2095/2023
|
Rajasthan Urja Vikas Nigam Ltd.
|
Petition seeking approval of procurement of 490 MW Hybrid power (Solar plus PSP) from Solar Energy Corporation of India Limited (SECI) under the competitive bidding conducted by SECI whereunder Greenko Energies Private Limited has offered to supply 490 MW energy to the petitioner for its consumption through Discoms
|
10/10/2023
|
|
61
|
2158/2023
|
Tarini Minerals
|
Petition filed under Section 86(1) (f) of the Electricity Act
|
10/10/2023
|
|
62
|
2159/2023
|
Tarini Minerals
|
Petition filed under Section 86(1) (f) of the Electricity Act
|
10/10/2023
|
|
63
|
2160/2023
|
Indrani Patnaik
|
Petition filed under Section 86(1) (f) of the Electricity Act
|
10/10/2023
|
|
64
|
2161/2023
|
Cepco Industries (P) Ltd
|
Petition filed under Section 86(1) (f) of the Electricity Act
|
10/10/2023
|
|
65
|
2162/2023
|
Nahar Colour and Coating Ltd.
|
Petition filed under Section 86(1) (f) of the Electricity Act
|
10/10/2023
|
|
66
|
2163/2023
|
Orient Glazes Ltd
|
Petition filed under Section 86(1) (f) of the Electricity Act
|
10/10/2023
|
|
67
|
2164/2023
|
Altrade Minerals (P) Ltd.
|
Petition filed under Section 86(1) (f) of the Electricity Act
|
10/10/2023
|
|
68
|
2165/2023
|
K.K. Enterprises
|
Petition filed under Section 86(1) (f) of the Electricity Act
|
10/10/2023
|
|
69
|
2099/2023
|
Discoms
|
Petition filed for amendment in Regulation 45, 46, 50 and 55 of the Rajasthan Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2019 with regard to the determination of fixed or capacity charges of Thermal Generating Stations.
|
10/10/2023
|
|
70
|
2166/2023
|
Suo Motu
|
Rajasthan Electricity Regulatory Commission (Service) (Seventh Amendment) Regulations, 2023
|
10/10/2023
|
|
71
|
2081/2023
|
J. K. Cement Limited
|
Petition challenging the monthly method of calculation of maximum capacity utilization factor for BTM solar P.V. Power Plant whereby the Respondents have applied it on a monthly basis under section 86(1)(f) of the Electricity Act 2003.
|
04/10/2023
|
|
72
|
2105/2023
|
Ajmer Gases
|
Petition for adjudicate the dispute and seeking direction with regard to the RE power adjustment by considering CUF on annual basis and applicability of CUF at drawl end.
|
04/10/2023
|
|
73
|
2156/2023
|
Suo motu
|
In the matter of RERC (Terms and Conditions of determination of Tariff) (3rd amendment) Regulations, 2023.
|
21/09/2023
|
|
74
|
1553/2019
|
Sh. D. P. Chirania and Ors.
|
Petition filed under section 142 of the Electricity Act, 2003 in the matter of non-compliance of Commission order dated 07.03.2019.
|
20/09/2023
|
|
75
|
2043/2022
|
Discoms
|
Petition filed under 86 (1) and 181 of the Electricity Act, 2003 and all other provisions enabling in this behalf for notification of Smart Grid Regulations.
|
20/09/2023
|
|
76
|
2140/2023
|
Rajasthan Urja Vikas Nigam Ltd
|
Petition filed for extension of power purchase agreements (PPAs) of 12 Generators in terms of RERC (Terms and Conditions of Tariff determination from Renewable Energy Sources) Regulations, 2020.
|
20/09/2023
|
|
77
|
2137/2023
|
Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
|
Petition filed for Amendment in Rajasthan Electricity Grid Code Under Section 181, read with section 86(1)(h) of the Electricity Act, 2003 and all other powers enabling it in this behalf.
|
12/09/2023
|
|
78
|
2077/2023
|
Link Enterprises
|
Petition filed in the matter of adjudication of dispute for Non Payment of Principal and LPS amount.
|
11/09/2023
|
|
79
|
2078/2023
|
Link Enterprises
|
Petition filed in the matter of adjudication of dispute for Non Payment of Principal and LPS amount.
|
11/09/2023
|
|
80
|
2085/2023
|
Arora Textiles Pvt. Ltd.
|
Petition filed in the matter of adjudication of dispute for Non Payment of Principal and LPS amount.
|
11/09/2023
|
|
81
|
2086/2023
|
Arora Textiles Pvt. Ltd.
|
Petition filed in the matter of adjudication of dispute for Non Payment of Principal and LPS amount.
|
11/09/2023
|
|
82
|
2088/2023
|
Avon Cycles Ltd.
|
Petition filed in the matter of adjudication of dispute for Non Payment of Principal and LPS amount.
|
11/09/2023
|
|
83
|
2089/2023
|
Avon Cycles Ltd.
|
Petition filed in the matter of adjudication of dispute for Non Payment of Principal and LPS amount.
|
11/09/2023
|
|
84
|
2124/2023
|
Rajasthan Rajya Vidyut Utpadan Nigam Ltd
|
Petition for In-principle approval for availing construction power to comply the MOEFCC guidelines on revised emission norms installation of FGD System for the RVUN Power Station
|
06/09/2023
|
|
85
|
2118/2023
|
Suo Motu
|
In the matter of the RERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) (First Amendment) Regulations, 2023
|
04/09/2023
|
|
86
|
2048/2022
|
ACME Jodhpur Solar Power Pvt. Ltd. and Ors.
|
Petition for seeking directions to Respondents to comply with Grid Code and take permanent measures to overcome the issue of consistent voltage tripping at the 220kV Bhadla Grid Sub-station and to compensate the Petitioners towards loss of revenue.
|
01/09/2023
|
|
87
|
2128/2023
|
Adani Power Rajasthan Limited.
|
Petition filed under Section 86(1)(f) and other applicable provisions of the Electricity Act, 2003 for adjudication of disputes with respect to excess payment made by the Petitioners to the Respondent on account of payment towards energy charge and change in law and respective adjustments
|
01/09/2023
|
|
88
|
2117/2023
|
Suo Motu
|
In the matter of the RERC (Grid Interactive Distributed Renewable Energy Generating Systems) (First Amendment) Regulations, 2023
|
28/08/2023
|
|
89
|
2138/2023
|
Rajasthan Urja Vikas Nigam Ltd.
|
Petition for seeking approval of deviations, along with justifications in the Model Bidding Document for procurement of 160 MW RTC power for 5 years on the basis of the Model Bidding documents.
|
23/08/2023
|
|
90
|
2133/2023
|
Sh. Bhanwar Lal Sharma
|
In the matter of Petition filed under Section 142 and146 of the Electricity Act, 2003 for non-compliance of Section 126 (3) of the Electricity Act 2003 and Regulation 12.2 and 12.3 of the RERC (Electricity Supply Code and Connected Matters) Regulations, 2021.
|
18/08/2023
|
|
91
|
2134/2023
|
Sh. Ashok Kumar
|
In the matter of Petition filed under Section 142 and146 of the Electricity Act, 2003 for non-compliance of Section 126 (3) of the Electricity Act 2003 and Regulation 12.2 and 12.3 of the RERC (Electricity Supply Code and Connected Matters) Regulations, 2021.
|
18/08/2023
|
|
92
|
2141/2023
|
M/s Mohan Lal Uttam Chand
|
In the matter of Petition filed under Section 142 and146 of the Electricity Act, 2003 for non-compliance of Section 126 (3) of the Electricity Act 2003 and Regulation 12.2 and 12.3 of the RERC (Electricity Supply Code and Connected Matters) Regulations, 2021.
|
18/08/2023
|
|
93
|
2051/2022
|
Rajasthan Urja Vikas Nigam Limited
|
In the matter of Petition under Section 86(1) (b) of the Electricity Act, 2003 read with Regulation 10 of the Rajasthan Electricity Regulatory Commission (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2020 for approval of power procurement from renewable sources.
|
08/08/2023
|
|
94
|
2018/2022
|
Palimarwar Solar House Private Limited
|
In the matter of petition filed under Section 86 (1) (f) read with Section 142 of the Electricity Act for adjudication of dispute
|
07/08/2023
|
|
95
|
2058/2022
|
Discoms
|
Petition filed under section 86 (1) and 181 of the Electricity Act, 2003 read with regulations 12.2, 12.3, 12.4, 12.5 and 14.1 of RERC (Electricity Supply Code and Connected Matters) Regulations, 2021 to obtain clarity and remove the difficulties faced by Discoms in implementation of the said regulations regarding assessment made in vigilance cases booked under Section 135 and 126 of the Electricity Act, 2003.
|
03/08/2023
|
|
96
|
2139/2023
|
Rajasthan Urja Vikas Nigam Ltd.
|
Petition under Section 86(1)(b) of the Electricity Act, 2003 for approval of power procurement from renewable sources
|
27/07/2023
|
|
97
|
2090/2023
|
NTPC Vidyut Vyapar Nigam Limited
|
Petition under Section 86 (1)(c) and (f) of the Electricity Act, 2003 for adjudication of disputes
|
27/07/2023
|
|
98
|
2122/2023
|
Rajasthan Textile Mills
|
Petition filed under section 45 (3)(b) of the Electricity Act, 2003, Regulation 10.8 of RERC (Electricity Supply Code and Connected Matters)Regulations, 2021 and clause 33 (5) of TCOS,2004 read with Section 142 of the Electricity Act, 2003 for payment of interest on excess tariff recovered from the date of recovering and withholding the amount in excess of the prescribed tariff.
|
24/07/2023
|
|
99
|
1960/2021
|
Ajeet SEEDs Pvt. Ltd.
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
100
|
2033/2022
|
Wind World Wind farms (Jaisalmer) Pvt Ltd
|
Petition filed under Section 142 of the Electricity Act 2003 for non compliance of Commissions order (LPS)
|
19/07/2023
|
|
101
|
2034/2022
|
Vaayu India Power Corporation Pvt Ltd
|
Petition filed under Section 142 of the Electricity Act 2003 for non compliance of Commissions order (LPS)
|
19/07/2023
|
|
102
|
2035/2022
|
Wind World Wind Farms (Rajasthan) Pvt Ltd.
|
Petition filed under Section 142 of the Electricity Act 2003 for non compliance of Commissions order (LPS)
|
19/07/2023
|
|
103
|
2036/2022
|
Wind World Wind Farms (Hindustan) Pvt Ltd
|
Petition filed under Section 142 of the Electricity Act 2003 for non compliance of Commissions order (LPS)
|
19/07/2023
|
|
104
|
2037/2022
|
Wind World Wind Farms (Temdarai) Pvt Ltd
|
Petition filed under Section 142 of the Electricity Act 2003 for non compliance of Commissions order (LPS)
|
19/07/2023
|
|
105
|
2038/2022
|
Vish Wind Infrastructure LLP
|
Petition filed under Section 142 of the Electricity Act 2003 for non compliance of Commissions order (LPS)
|
19/07/2023
|
|
106
|
1971/2021
|
Avon Cycles Ltd.
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
107
|
1999/2022
|
Avon Cycles Ltd.
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
108
|
1973/2021
|
Link Enterprises
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
109
|
1976/2021
|
Link Enterprises
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
110
|
1977/2021
|
Maxwell Inc.
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
111
|
1982/2022
|
Mukand Industries Pvt Ltd.
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
112
|
1983/2022
|
Arora Textiles Pvt Ltd
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
113
|
1984/2022
|
Arora Textiles Pvt Ltd
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
114
|
1986/2022
|
Kundan Care Products Ltd
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
115
|
1994/2022
|
Bhabani Pigments Pvt Ltd
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
116
|
1996/2022
|
Kukreja Builders Pvt Ltd.
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
117
|
1997/2022
|
Emerald Electronics Pvt Ltd.
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
118
|
2008/2022
|
Pawan Enterprises
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
119
|
2049/2022
|
Western Drugs Ltd.
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
120
|
2002/2022
|
Ushdev Engitech Ltd.
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
121
|
2003/2022
|
Ushdev Engitech Ltd.
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
122
|
2004/2022
|
Ushdev Engitech Ltd.
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
123
|
2005/2022
|
Ushdev Windpark Ltd.
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
124
|
2006/2022
|
Ushdev Windpark Ltd.
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
125
|
2007/2022
|
Ushdev Windpark Ltd.
|
Adjudication of dispute (LPS)
|
19/07/2023
|
|
126
|
2087/2023
|
TP Ajmer Distribution Limited
|
Petition seeking directions to the Respondent, inter alia to implement the Revamped Distribution Sector Scheme (RDSS)
|
18/07/2023
|
|
127
|
2125/2023
|
Indian Medical Association, Rajasthan.
|
In the matter of review of the Commission order dated 31.03.2023 passed in the petition No. 2066/22, 2067/22 and 2068/22 and for reclassification of tariff applicable to the hospitals / nursing homes / dispensaries / clinics run by the members of the Indian Medical Association, Rajasthan
|
17/07/2023
|
|
128
|
2054/2022
|
Malaxmi Wind Power
|
In the matter of Petition filed under section 142 of the Electricity Act 2003 for not following the direction to release late payment surcharge (LPS)
|
04/07/2023
|
|
129
|
2059/2022
|
SBF Ispat Private Limited
|
Corrigendum Petition for review of Commissions order dated 01.09.2022 to recognize additional power purchase cost in the matter of Change in Law and allow recovery of additional power purchase cost through special FSA.
|
04/07/2023
|
|
130
|
2060/2022
|
Hindustan Zinc Limited
|
Corrigendum Petition for review of Commissions order dated 01.09.2022 to recognize additional power purchase cost in the matter of Change in Law and allow recovery of additional power purchase cost through special FSA.
|
04/07/2023
|
|
131
|
2062/2022
|
Rajasthan Textile Mills Association
|
Corrigendum Petition for review of Commissions order dated 01.09.2022 to recognize additional power purchase cost in the matter of Change in Law and allow recovery of additional power purchase cost through special FSA.
|
04/07/2023
|
|
132
|
2092/2023
|
Shree Cement Limited
|
Petition for seeking directions/clarification and removal of difficulty with respect to the levy, along with review, of Special Fuel Surcharge Adjustment (FSA)
|
03/07/2023
|
|
133
|
2091/2023
|
Rajendra Kumar Arora, Beawar
|
Petition filed under Section 142 and146 of the Electricity Act, 2003 for non-compliance of Section 126 (3) of the Electricity Act 2003 and Regulation 10 and 12 of the RERC (Electricity Supply Code and Connected Matters) Regulations, 2021
|
03/07/2023
|
|
134
|
2094/2023
|
Sh. Madan Lal Marothiya, Beawar
|
Petition filed under Section 142 and146 of the Electricity Act, 2003 for non-compliance of Section 126 (3) of the Electricity Act 2003 and Regulation 10 and 12 of the RERC (Electricity Supply Code and Connected Matters) Regulations, 2021
|
03/07/2023
|
|
135
|
1992/2022
|
Sayar Engineering Private Limited
|
Petitions filed under Section 142 and 146 of the Electricity Act due to non-compliance of section 126(3) and 56 (1) of the Act and RERC( Supply Code and Connected Matter) Regulations, 2004 and 2021
|
28/06/2023
|
|
136
|
2021/2022
|
Sun N Sand Hotels Pvt Ltd
|
Petition filed under Section 142 of the Electricity Act for not following the direction to release late Payment Surcharge
|
23/06/2023
|
|
137
|
2059/2022
|
SBF Ispat Private Limited
|
Petition for review of Commissions order dated 01.09.2022 to recognize additional power purchase cost in the matter of Change in Law and allow recovery of additional power purchase cost through special FSA.
|
23/06/2023
|
|
138
|
2060/2022
|
Hindustan Zinc Limited
|
Petition for review of Commissions order dated 01.09.2022 to recognize additional power purchase cost in the matter of Change in Law and allow recovery of additional power purchase cost through special FSA.
|
23/06/2023
|
|
139
|
2062/2022
|
Rajasthan Textile Mills Association
|
Petition for review of Commissions order dated 01.09.2022 to recognize additional power purchase cost in the matter of Change in Law and allow recovery of additional power purchase cost through special FSA.
|
23/06/2023
|
|
140
|
2093/2023
|
Shree Cement Ltd.
|
Petition for removal of difficulty in implementation of RERC Open Access Regulations, 2016
|
16/06/2023
|
|
141
|
1371/2018
|
Ramayana Ispat Private Limited
|
Petition filed for review of eleventh amendment of RERC (Electricity Supply Code and Connected Matters) Regulations, 2004.
|
16/06/2023
|
|
142
|
2052/2022
|
Ramayana Ispat Private Limited
|
Petition under Section 86(1)(A), Section 62(6), Section 142 and Section 146 of the Electricity Act, 2003 read with various tariff orders passed by the Commission from time to time.
|
16/06/2023
|
|
143
|
2126/2023
|
Jaipur Vidyut Vitran Nigam Limited.
|
Petition for for Approval of Levelized Tariff discovered through transparent Competitive Bidding carried out by JVVNL for Solar Power Projects With Aggregate Capacity of 52.66 MW under Component-C (Feeder Level Solarization) of PM-KUSUM Scheme.
|
16/06/2023
|
|
144
|
2079/2023
|
Suo Motu
|
RERC (Renewable Purchase Obligation) Regulations, 2023
|
13/06/2023
|
|
145
|
509/2015
|
National Engineering Industries Ltd.
|
Adjudication of dispute and seeking clarifications on applicability of wheeling losses on interstate open access.
|
01/06/2023
|
|
146
|
560/2015
|
R. M. Mittal Steels Pvt. Ltd.
|
Adjudication of dispute and seeking clarifications on applicability of wheeling losses on interstate open access.
|
01/06/2023
|
|
147
|
2000/2022
|
Jaipur Vidyut Vitran Nigam Limited and Ors
|
Petition filed under Regulation 17 of RERC (Grid interactive Distributed Renewable Energy Generating Systems) Regulations, 2021 read with Commissions order dated 07.09.2021 to make necessary amendments in the said Regulations to alleviate the problems faced by Discoms due to Netmetered consumers.
|
01/06/2023
|
|
148
|
2061/2022
|
Parsolar Pvt. Ltd.
|
Petition filed in the matter of adjudication of dispute under section 86(1)(f) of the Electricity Act, 2003.
|
31/05/2023
|
|
149
|
1911/2021
|
Discoms
|
Petition for necessary Amendments in RERC (Forecasting, Scheduling, Deviation Settlement and related Matters of Solar and Wind Generation Sources) Regulations, 2017.
|
24/05/2023
|
|
150
|
2073/2022
|
APM Industries Limited
|
Non compliance of Ombudsman order
|
18/05/2023
|
|
151
|
2100/2023
|
Discoms
|
Petition filed for amendment in Regulation 88 of the RERC (Terms and Conditions for Determination of Tariff) Regulations, 2019.
|
05/05/2023
|
|
152
|
2098/2023
|
Rajasthan Urja Vikas Nigam Limited.
|
Petition filed for Energy Assessment Committee (EAC) approval till 2029-30.
|
05/05/2023
|
|
153
|
1949/2021
|
Ajmer Vidyut Vitran Nigam Ltd.
|
In the matter of Petition under regulation 30(3) of the RERC (Terms and Conditions for Open Access) Regulations, 2016, against the order dated 17.12.2018 passed by SLDC settling the UI accounts.
|
05/05/2023
|
|
154
|
2025/2022
|
Suo-moto
|
In the matter of RERC (Electricity Supply Code and Connected Matters) (First Amendment) Regulations, 2023
|
20/04/2023
|
|
155
|
2113/2023
|
Suo Motu
|
In the matter of designating Rajasthan Vidyut Utpadan Nigam as the Nodal Agency in respect of the development of the Renewable Energy Projects being implemented by RVUNL in the Rajasthan State.
|
13/04/2023
|
|
156
|
2072/2022
|
Rajasthan Rajya Vidyut Prasaran Nigam Ltd
|
Review of Commissions order 07.09.2022 in the matter of approval of revised threshold limit to Rs. 250 Crore instead of Rs. 100 Crore for development of intra-state Transmission Projects through Tariff Based Competitive Bidding.
|
12/04/2023
|
|
157
|
2112/2023
|
Suo Motu
|
In the matter of Directives issued by the Commission in the matter of determination of ARR and Tariff Order dated 31.03.2023
|
12/04/2023
|
|
158
|
2097/2023
|
Rajasthan Urja Vikas Nigam Ltd
|
Petition for approval of 160 MW power procurement for 5 years on the basis of medium-term power procurement guidelines issued by the Ministry of Power, Government of India.
|
31/03/2023
|
|
159
|
2044/2022
|
Clean Solar Power (Bhainsada) Private Limited
|
Petition under Section 86(1)(b) and (f) of the Electricity Act, 2003 for approval of change in law and seeking an appropriate mechanism for grant of appropriate adjustment /compensation to offset financial commercial impact of change in law events
|
29/03/2023
|
|
160
|
2053/2022
|
ACME Aklera Power Technology Private Limited
|
Petition for in-principle approval of Change in Law, adoption of the mechanism provided under the Electricity (Timely Recovery of Costs due to Change in Law) Rules 2021 for appropriate adjustment / compensation to offset financial / commercial impact of change in law events.
|
27/03/2023
|
|
161
|
2057/2022
|
Hindustan Zinc Limited
|
Petition filed under section 47, 86 and other applicable provisions of the Electricity Act, 2003 seeking provision of security in the form of furnishing Bank Guarantee/Letter of Credit in lieu of cash deposit.
|
20/03/2023
|
|
162
|
1958/2021
|
Rajasthan Rajya vidyut prasaran Nigam Ltd.
|
Petition for removal of difficulties and seeking clarification of transmission charges and various other charges to be levied on Indian Railway (deemed licensee), DFCCIL and other similar entities for availing open access.
|
16/03/2023
|
|
163
|
577/2015
|
Adani Power Rajasthan Limited
|
Determination of compensation/carrying cost on account of Change in Law
|
16/03/2023
|
|
164
|
2083/2023
|
H M Food Produst
|
Petition filed for non - Compliance Of RERC Notification No. RERC/Secy/Reg. 143 Ajmer Discom, Ajmer.
|
17/02/2023
|
|
165
|
2084/2023
|
Kunal Industries
|
Petition filed for non - Compliance Of RERC Notification No. RERC/Secy/Reg. 143 Ajmer Discom, Ajmer.
|
17/02/2023
|
|
166
|
503/2015
|
Ramayana Ispat Pvt. Ltd.
|
Petition filed under Section 86(1)(k) and Section 129 of Electricity Act, 2003 read with RERC(Terms and Condition for Open Access) Regulations, 2004 and RERC(Intra-State ABT) Regulations, 2006 regarding non settlement of UI account.
|
13/02/2023
|
|
167
|
2071/2022
|
Suo Motu
|
In the matter of RERC (Terms and Conditions of determination of Tariff) (2nd amendment) Regulations, 2022.
|
27/01/2023
|
|
168
|
1964/2021
|
Shri Rakesh Singh
|
Petition for review and rectification of errors in the levellised tariff fixed for PV Solar Power Plant to be set up under PM Kusum Yojna Component-A and for determination of compensation/adjustment in levellised tariff on account of Change in Law events
|
27/01/2023
|
|
169
|
2026/2022
|
Kisan Urja Hitkari Samiti
|
Petition filed under Section 62 (a) of the Electricity Act, 2003, for revision of levellised tariff from the COD due to increase in Capital cost of Ground Mounted PV Solar Power Plant to be set-up under PM Kusum Yojna Component-A
|
27/01/2023
|
|
170
|
2055/2022
|
Shree Cement Limited
|
Petition filed under section 142 Act for contravention of directions contained RERC Order for Multi Year Aggregate Revenue requirement, Tariff Petition and Investment Plan of Discoms for FY 2020-21 to 2023-24
|
17/01/2023
|
|
171
|
1937/2021
|
Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
|
Petition filed under section 181 of electricity Act 2003 read with Regulation 94 of RERC (terms and conditions for determination of Tariff) Regulations, 2019 and electricity (Late Payment Surcharge) Rules 2021
|
10/01/2023
|
|
172
|
1943/2021
|
JSW Energy (Barmer) Ltd.
|
Petition filed under section 86(1)(f) of electricity Act, 2003 for adjudication of dispute
|
10/01/2023
|
|
173
|
1961/2021
|
Rajasthan Urja Vikas Nigam Limited
|
Petition filed under Regulation 10 of RERC (Terms and Conditions for Determination of Tariff from Renewable Energy Sources) Regulations 2020 For Extension of Power Purchase Agreements of Wind Power Generators for a Period of 5 Years
|
04/01/2023
|
|
174
|
1966/2021
|
M/s ReNew Solar Energy (Jharkhand Five) Pvt. Ltd.
|
Petition under Section 86(1)(f) of the Electricity Act, 2003 seeking recovery of balance payment for the energy supplied from the Petitioners 110 MW solar power project.
|
21/12/2022
|
|
175
|
2029/2022
|
Ultimate Sun Systems Private Limited.
|
Petition for determination of compensation/adjustment in the levelised tariff fixed for 4.24 MW pilot Feeder level Solarization Project under Component-C of PM KUSUM Scheme on account of Change in Law events.
|
15/12/2022
|
|
176
|
2050/2022
|
Indian Medical Association, Rajasthan.
|
In the matter of reclassification of tariff applicable to the hospitals/nursing homes/dispensaries/clinics run by the members of the Indian Medical Association, Rajasthan presently categorized as Non-Domestic Services (Schedule NDS/LT-2) under Regulation 34, 43, 45 of RERC (Transaction of Business) Regulations, 2021 and section 61, 62 and 94(1)(f) of the Electricity Act, 2003 read with RERC (Terms and Conditions for Determination of Tariff) Regulations, 2019.
|
13/12/2022
|
|
177
|
1905/2021
|
Rajasthan Urja Vikas Nigam Limited
|
Corrigendum- In the matter of Petition filed under Section 63 of the Act for adoption of tariff for 1070 MW Solar PV Power
|
12/12/2022
|
|
178
|
1968/2021
|
Maharaja Shree Umaid Mills Ltd.
|
Petition under Section 94 (1)(f) of the Electricity Act for review read with Regulation 72, 73 and 74 of RERC (Transaction of Business) Regulations, 2005 for seeking clarifications and further guidance in the order dated 22.11.2021 of the Commission in petition No. RERC/1920/21.
|
05/12/2022
|
|
179
|
1925/2021
|
Vijay Solvex Limited
|
Petition for directions to amend the Wheeling and Banking Agreement (Extension of period from 20 years to 25 Years)
|
29/11/2022
|
|
180
|
2022/2022
|
Discoms
|
In the matter of petition filed under 86 (1) and 181 of the Electricity Act, 2003 and all other provisions enabling in this behalf for notification of Merit Order Despatch and optimization of power purchase.
|
29/11/2022
|
|
181
|
1959/2021
|
Maharaja Shree Umaid Mills Ltd
|
Petition filed under Section 94 (1)(f) of the Electricity Act for review read with Regulation 72, 73 and 74 of RERC (Transaction of Business) Regulations, 2005 for seeking clarifications and further guidance in the order dated 30.09.2021 of the Commission in petition No. RERC/1912/2021
|
29/11/2022
|
|
182
|
1927/2021
|
Deepak Vegpro Private Limited
|
Petition for directions to amend the Wheeling and Banking Agreement (Extension of period from 20 years to 25 Years)
|
15/11/2022
|
|
183
|
2017/2022
|
Rajasthan Urja Vikas Nigam Ltd.
|
Petition under Section 86 (1) (b) of the Electricity Act, 2003 for approval of 294 MW Round-the-clock (RTC) long-term power purchase and approval of deviations in the Model Bidding documents for long term Procurement of Electricity under DBFOO
|
02/11/2022
|
|
184
|
2040/2022
|
Discoms
|
Petition filed for allowing expenses incurred in execution of smart metering works
|
21/10/2022
|
|
185
|
2030/2022
|
Shree Cement Ltd.
|
Petition under section 98 Power to Remove Difficulties under RERC (Terms and Conditions for Tariff Determination from Renewable Energy Sources) Regulations, 2020
|
10/10/2022
|
|
186
|
1936/2021
|
Hindustan Zinc Ltd.
|
In the matter of Petition under Section 62, 86, 142 and other applicable provisions of the Electricity Act, 2003
|
06/10/2022
|
|
187
|
1827/2020
|
M/s Rajasthan Textile Mills Association and Others
|
Petition filed under section 86(1)(f) read with section 142 of the Act
|
27/09/2022
|
|
188
|
1917/2021
|
Lucid Colloids Limited
|
Petition filed under section 86(1)(f) read with section 142 of the Act
|
27/09/2022
|
|
189
|
1918/2021
|
Mewar Polytex Limited and Others
|
Petition filed under section 86(1)(f) read with section 142 of the Act
|
27/09/2022
|
|
190
|
1919/2021
|
PG Foils Limited
|
Petition filed under section 86(1)(f) read with section 142 of the Act
|
27/09/2022
|
|
191
|
1952/2021
|
Vedanta Limited
|
Petition filed under section 86(1)(f) read with section 142 of the Act
|
27/09/2022
|
|
192
|
2023/2022
|
Rajasthan Urja Vikas Nigam Ltd.
|
Petition filed under Section 63 of the Electricity Act, 2003 for adoption of tariff for 1785 MW solar power
|
27/09/2022
|
|
193
|
2046/2022
|
Jaipur Vidyut Vitran Nigam Ltd.
|
Petition filed under sections 14, 15 and 16 of Rajasthan Electricity Regulatory Commission (Standards of Performance for distribution licensees) Regulations, 2021 to allow necessary relaxations in the said Regulations
|
23/09/2022
|
|
194
|
1970/2021
|
Rambagh Eco Power Unit Of Rambagh Palace Hotel Pvt Ltd
|
Adjudication of dispute under section 86(1)(f) of the Electricity Act 2003
|
20/09/2022
|
|
195
|
1998/2022
|
Jaipur Vidyut Vitran Nigam Ltd. and Ors.
|
In the matter of petition for review of Commissions order dated 30.09.2021
|
19/09/2022
|
|
196
|
2042/2022
|
Discoms
|
Petition under Section 94(2) of the electricity act, 2003 read with Regulation 95 of the RERC( Terms and Conditions for determination of Tariff) Regulations, 2019 for providing temporary relief measures to alleviate the issues faced by Discoms in the current scenario of power crisis.
|
13/09/2022
|
|
197
|
2027/2022
|
Rajasthan Rajya Vidyut Prasaran Nigam Ltd.
|
Petition for revision of threshold limit to Rs 250 Crore for development of intra State Transmission Projects through Tariff Based Competitive Bidding (TBCB) Process alongwith criteria and exemptions.
|
07/09/2022
|
|
198
|
2024/2022
|
Discoms
|
Petition filed under Section 62 (4) of the Electricity Act, 2003 read with Regulation 88 of RERC (Terms and Conditions for Determination of Tariff) Regulations, 2019 to recognize Additional Power Purchase Cost incurred in order to comply with the orders of Honble Supreme Court in the matter of change in law and allow recovery of additional power purchase cost through special FSA.
|
01/09/2022
|
|
199
|
1905/2021
|
Rajasthan Urja Vikas Nigam Limited.
|
In the matter of Petition filed for adoption of tariff for 1070 MW Solar PV power under Section 63 of the Electricity Act, 2003
|
31/08/2022
|
|
200
|
1598/2020
|
Mahindra and Mahindra Ltd.
|
In the matter of under Section 62, 86(1)(a) and 142 of the Electricity Act, 2003 against the action of the Respondent for re-categorize from Large Industrial category to Non-Domestic category.
|
24/08/2022
|
|
201
|
1329/2018
|
JSW Energy (Barmer) Ltd.
|
Petition filed for in-principle approval of additional capitalization on account of up gradation of Electrostatic Precipitators and Lime Handling System
|
12/07/2022
|
|
202
|
1953/2021
|
Rajasthan Urja Vikas Nigam Ltd.
|
Petition filed under Section 86(1)(b) of the Electricity Act, 2003 to seek permission for procurement of 1200 MW Wind Power under ISTS Wind Trenche-X
|
23/06/2022
|
|
203
|
2015/2022
|
Bhagirath Natural Stones Industries
|
Petitions for non-compliance of Section 171, Section 56 of the Electricity Act, 2003 and Reg. 139 Electricity Supply Code and Connected Matters Regulation, 2021
|
09/06/2022
|
|
204
|
2016/2022
|
Bhagirath Natural Stones Industries
|
Petitions for non-compliance of Section 171, Section 56 of the Electricity Act, 2003 and Reg. 139 of Electricity Supply Code and Connected Matters Regulation, 2021
|
09/06/2022
|
|
205
|
2010/2022
|
Rajasthan Urja Vikas Nigm Ltd.
|
Petition for approval of procurement of 490 MW hybrid power (Solar plus PSP) from SECI under the competitive bidding
|
12/05/2022
|
|
206
|
1535/2019
|
Rajasthan Textile Mills
|
Petitions filed under Section 142 of the Electricity Act, 2003 for non-compliance of Ombudsmans order
|
12/05/2022
|
|
207
|
2019/2022
|
Discoms
|
Petition for amendments in RERC (Electricity Supply Code And Connected Matters) Regulations,2021
|
10/05/2022
|
|
208
|
1817/2020
|
Shree Cement Limited
|
Petition seeking amendments in Regulation 11 (5) and 21 (i), 21 (iii) of RERC(Terms and Conditions for Open Access) Regulations, 2016
|
31/03/2022
|
|
209
|
1962/2021
|
Suo Motu
|
In the matter of proposed Amendments in the Procedure for implementation of the Framework on Forecasting and Scheduling for Renewable Energy (RE) Generating Stations (Wind and Solar)
|
31/03/2022
|
|
210
|
1967/2021
|
Jaipur Vidyut Vitran Nigam Ltd.
|
Petition filed for review of Commissions order dated 02/11/2021.
|
15/03/2022
|
|
211
|
1995/2022
|
Rajasthan Urja Vikas Nigam Ltd.
|
Petition under Section 86(1)(b) of the Electricity Act, 2003 for approval of power procurement from renewable sources.
|
08/03/2022
|
|
212
|
1989/2022
|
Jaipur Vidyut Vitran Nigam Ltd.
|
Petition for approval of levelized tariff discovered through transparent competitive bidding carried out by JVVNL for 4.24 MW pilot Solar Power Project for feeder level solarization under Component-C of PM-KUSUM scheme
|
07/03/2022
|
|
213
|
1898/2021
|
Indian Wind Energy Association and ors.
|
Removal of difficulties in RERC (Terms and Conditions for Tariff Determination from Renewable Energy Sources) Regulations, 2020
|
28/02/2022
|
|
214
|
1899/2021
|
IB Vogt Solar Eight Pvt. Ltd.
|
Removal of difficulties in RERC (Terms and Conditions for Tariff Determination from Renewable Energy Sources) Regulations, 2020
|
28/02/2022
|
|
215
|
1924/2021
|
Rajasthan Solar Association
|
Removal of difficulties in RERC (Terms and Conditions for Tariff Determination from Renewable Energy Sources) Regulations, 2020
|
28/02/2022
|
|
216
|
1969/2021
|
Discoms
|
Petition for amendments in RERC (Standards of Performance for Distribution Licensees) Regulations, 2021
|
22/02/2022
|
|
217
|
1931/2021
|
Rajasthan Rajya Vidyut Prasaran Nigam Ltd.
|
Petition filed for deferment and amendment in SOP Regulations, 2021
|
21/02/2022
|
|
218
|
1938/2021
|
Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
|
In the matter of extension of infirm power period for Suratgarh Super Critical Thermal Power Station (SSTPS) Unit-8
|
17/02/2022
|
|
219
|
1858/2020
|
SBE Renewables Twenty Two C1 Pvt. Ltd
|
Petitions filed for removal of difficulties in RERC (Terms and Conditions for Tariff Determination from Renewable Energy Sources)Regulations,2020
|
11/01/2022
|
|
220
|
1859/2020
|
SBE Renewables Twenty Two C2 Pvt. Ltd
|
Petitions filed for removal of difficulties in RERC (Terms and Conditions for Tariff Determination from Renewable Energy Sources)Regulations,2020
|
11/01/2022
|
|
221
|
1860/2020
|
SBE Renewables Twenty Two C3 Pvt. Ltd
|
Petitions filed for removal of difficulties in RERC (Terms and Conditions for Tariff Determination from Renewable Energy Sources)Regulations,2020
|
11/01/2022
|
|
222
|
1861/2020
|
SBE Renewables Twenty Two C4 Pvt. Ltd
|
Petitions filed for removal of difficulties in RERC (Terms and Conditions for Tariff Determination from Renewable Energy Sources)Regulations,2020
|
11/01/2022
|
|
223
|
1914/2021
|
Fortum Solar Plus Private Limited
|
Petition filed for declaration of Change in Law Events, viz., the imposition of Safeguard Duty and increase in Basic Custom Duty
|
30/12/2021
|
|
224
|
1922/2021
|
ReNew Solar Energy (Jharkhand Five) Pvt. Ltd.
|
Petition filed for declaration of Change in Law Events, viz., the imposition of Safeguard Duty and increase in Basic Custom Duty
|
30/12/2021
|
|
225
|
1941/2021
|
Sitara Solar Energy Pvt Ltd.
|
Petition filed for declaration of Change in Law Events, viz., the imposition of Safeguard Duty and increase in Basic Custom Duty
|
30/12/2021
|
|
226
|
1907/2021
|
Suo Motu
|
Discussion Paper on Framework for Large Scale Integration of Renewable Energy using Energy Storage Systems and its impact on Tariffs.
|
30/12/2021
|
|
227
|
1948/2021
|
Rajasthan Urja Vikas Nigam Ltd.
|
Petition filed for approval of draft Bidding Documents (RFQ, RFP and APP) and approval for procurement of up to 266 MW RTC power on long term basis from domestic fuel (Coal or Lignite) based power generating stations for meeting the requirement of Discoms.
|
30/12/2021
|
|
228
|
1939/2021
|
Rajasthan Urja Vikas Nigam Ltd.
|
Petition to waive off the shortfall of the Renewable Purchase Obligations ought to be complied by the Discoms accruing from the year 2011-2012
|
23/12/2021
|
|